Jobsite Math: 14 Formulas Crews Use Every Week
The jobsite calculator formulas for concrete, lumber, layout, stairs, wire and HVAC, each with one worked example and the code section where one applies.

Every jobsite calculator runs on a short list of formulas. These are the fourteen that come up most across construction, electrical, HVAC and plumbing work, each with the formula, one worked example, and the code section it answers to where there is one. Where a formula needs more than a paragraph, the full guide is linked.
Verify before you build. Code sections and table values change between editions, and jurisdictions adopt them with local amendments. Treat this page — and the app — as a calculation aid, not as the code book: confirm every number against the edition your authority having jurisdiction enforces. How FieldDojo validates its calculations.
| # | Calculation | Formula |
|---|---|---|
| 1 | Concrete volume | L × W × T (ft) ÷ 27 = cubic yards |
| 2 | Board feet | T (in) × W (in) × L (ft) ÷ 12 |
| 3 | Square check | diagonal = √(a² + b²) |
| 4 | Rafter length | √(run² + rise²) |
| 5 | Stair risers | total rise ÷ max riser, rounded up |
| 6 | Baluster count | n > (opening − max gap) ÷ (width + max gap) |
| 7 | Miter setting | 180° ÷ sides, or 90° − corner ÷ 2 |
| 8 | Drawing scale | real = drawing × 12 ÷ scale inches |
| 9 | Arc radius | R = c² ÷ (8h) + h ÷ 2 |
| 10 | Breaker size | continuous amps × 1.25 + non-continuous amps |
| 11 | Voltage drop | VD = 2 × K × I × L ÷ CM |
| 12 | Conduit fill | sum of wire areas ÷ conduit area ≤ 40% |
| 13 | Cooling tons | BTU/h ÷ 12,000 |
| 14 | Drain slope | fall = run (ft) × ¼ in |
Construction and Layout
1. Concrete Volume
Cubic yards = length × width × thickness (all in feet) ÷ 27A 10 × 12 ft slab, 4 in thick: 10 × 12 × 0.333 = 40 cubic feet. 40 ÷ 27 = 1.48 cubic yards. Add 5 to 10% for an uneven subgrade and spillage, which brings the order to about 1.6 yards. Convert the thickness to feet before you multiply; mixing inches and feet is the most common error. Footings, walls and round piers are in the concrete guide.
2. Board Feet
Board feet = thickness (in) × width (in) × length (ft) ÷ 12One 2 × 8 at 12 ft: 2 × 8 × 12 ÷ 12 = 16 board feet. Lumber sold by the board foot is figured on nominal dimensions. Multiply by the piece count, then by the price per board foot.
3. Square Check (3-4-5)
Diagonal = √(side a² + side b²)A 12 × 16 ft deck frame is square when both diagonals measure √(144 + 256) = √400 = 20 ft. That is the 3-4-5 triangle scaled by four. On a frame with no clean multiple, such as 10 × 14 ft, the diagonal is 17.205 ft, which is 17 ft 2 7⁄16 in. Pull both diagonals and adjust until they match.
4. Rafter Length
Rafter length = √(run² + rise²), rise = run × pitch ÷ 12A 6-in-12 roof over a 12 ft run rises 6 ft. √(144 + 36) = 13.42 ft, or 13 ft 5 in along the rafter line. That is the line length from the ridge centre to the outside of the wall plate. Take off half the ridge thickness and add the overhang before you cut.
5. Stair Risers
Risers = total rise ÷ maximum riser height, rounded up
Riser height = total rise ÷ risersA 108 in floor-to-floor rise under the IRC’s 7¾ in maximum (R311.7.5.1): 108 ÷ 7.75 = 13.94, so 14 risers at 108 ÷ 14 = 7.71 in, about 7 11⁄16 in. There is one tread fewer than risers, each at least 10 in deep (R311.7.5.2). Limits for Canada and the UK, and the comfort rule, are in the stair guide; the stair calculator runs it in the browser.
6. Baluster Count
n > (opening − max gap) ÷ (baluster width + max gap)
Gap = (opening − n × width) ÷ (n + 1)A 72 in clear opening with 1½ in balusters and the IRC’s 4 in sphere rule (R312.1.3): (72 − 4) ÷ 5.5 = 12.4, so 13 balusters with 3¾ in gaps. A gap of exactly 4 in fails. The baluster spacing guide has the stair exception and a table of common sections.
7. Miter Setting
Closed frame of N equal sides: saw setting = 180° ÷ N
Two pieces meeting at corner angle A: saw setting = 90° − A ÷ 2An octagon: 180 ÷ 8 = 22.5° on both ends of every piece. A bay-window corner measured at 135°: 90 − 67.5 = 22.5° on each piece. Both settings are read from a square cut, which is how a miter saw’s scale is marked. These are flat miters; crown and compound cuts need a bevel as well. Side lengths and the settings for other shapes are in the miter angle guide.
8. Drawing Scale
Real length = drawing length × 12 ÷ scale inches (for x in = 1 ft 0 in)At ¼ in = 1 ft the multiplier is 12 ÷ 0.25 = 48. A wall that measures 3½ in on the sheet is 3.5 × 48 = 168 in, 14 ft. At ⅛ in scale the multiplier is 96. Scale from a printed sheet only when it was printed at full size; a PDF shrunk to fit the paper changes the scale without saying so.
9. Arc Radius From Chord and Rise
Radius = chord² ÷ (8 × rise) + rise ÷ 2An arched opening 36 in wide that rises 6 in at the centre: 36² ÷ 48 + 3 = 27 + 3 = 30 in radius. Set trammel points to 30 in and the arc lands on both spring points and the crown. To bend a board to that radius, see the kerf bending guide.
Electrical
10. Breaker Size
Minimum rating = continuous load × 1.25 + non-continuous loadA 48 A EV charger is a continuous load: 48 × 1.25 = 60 A, which is a standard rating in NEC 240.6(A). The rule is NEC 210.20(A). Round up to the next standard rating, then check that the conductor is good for it. The breaker sizing guide and the breaker size calculator cover the conductor check.
11. Voltage Drop
VD = 2 × K × I × L ÷ CM (single phase; K = 12.9 for copper, 21.2 for aluminum)I is the load in amps, L the one-way length in feet, CM the conductor’s circular mils. A 16 A load, 100 ft away, at 120 V:
| Conductor | Circular mils | Drop | Percent |
|---|---|---|---|
| 12 AWG | 6,530 | 6.32 V | 5.3% |
| 10 AWG | 10,380 | 3.98 V | 3.3% |
| 8 AWG | 16,510 | 2.50 V | 2.1% |
The NEC’s informational note to 210.19 recommends 3% on a branch circuit, so this run wants 8 AWG, two sizes above what ampacity alone requires. The wire sizing guide, the voltage drop calculator and the voltage drop chart go further.
12. Conduit Fill
Fill = total conductor area ÷ conduit internal area (40% maximum for three or more conductors)½ in EMT has 0.304 in² of internal area, so 40% is 0.122 in². A 12 AWG THHN conductor is 0.0133 in². 0.122 ÷ 0.0133 = 9.1, so nine fit. The percentages are in NEC Chapter 9 Table 1: 53% for one conductor, 31% for two, 40% for more. Mixed sizes and the nipple exception are in the conduit fill guide.
HVAC and Plumbing
13. Cooling Tons and Airflow
Tons = BTU/h ÷ 12,000 Airflow ≈ 400 CFM per tonA 36,000 BTU/h cooling load is 3 tons and about 1,200 CFM of supply air. The division is exact, since a ton of cooling is defined as 12,000 BTU/h. The hard part is the load itself, which comes from a room-by-room calculation and not from square footage. See the Manual J guide, and the duct sizing guide for moving the air.
14. Drain Slope
Fall = run in feet × slope per footHorizontal drains 2½ in and smaller slope ¼ in per foot under IPC Table 704.1, and UPC 708.1 sets the same ¼ in as its standard. A 20 ft run of 2 in drain falls 20 × ¼ = 5 in from end to end. Larger pipe is allowed flatter: ⅛ in per foot for 3 to 6 in pipe under the IPC. Fixture units and pipe sizes are in the pipe sizing guide.
Frequently Asked Questions
What math is used most on a jobsite?
Area and volume for ordering material, the Pythagorean theorem for squaring and for rafters and stairs, division with rounding up for counts such as risers, balusters and boards, and a few trade formulas with code limits attached: breaker sizing, voltage drop, conduit fill and drain slope.
How do you check that a foundation or deck is square?
Measure both diagonals. They are equal when the frame is square, and each equals the square root of the length squared plus the width squared. For a quick check on one corner, mark 3 ft along one side and 4 ft along the other; the distance between the marks is 5 ft when the corner is 90°.
How many cubic yards of concrete are in a 10 × 12 slab?
At 4 inches thick, 1.48 cubic yards: 10 × 12 × 0.333 ÷ 27. At 6 inches thick it is 2.22 cubic yards. Add 5 to 10% before ordering.
What is the formula for voltage drop?
For a single-phase circuit, VD = 2 × K × I × L ÷ CM, where K is 12.9 for copper or 21.2 for aluminum, I is the current in amps, L is the one-way length in feet and CM is the conductor’s area in circular mils from NEC Chapter 9 Table 8.
What is a jobsite calculator?
A jobsite calculator is a calculator, as a handheld unit or a phone app, built for trade math in place of general arithmetic: it works in feet, inches and fractions, knows formulas such as the ones on this page, and returns an answer in the units the work is ordered or built in. A code-referenced one also shows the code section a result has to meet.
How FieldDojo Handles This
FieldDojo is a free jobsite calculator app with 65 calculators across construction, electrical, HVAC and plumbing, including every formula on this page. Each result shows the formula with your numbers in it and the code section behind it, comes with a drawing, and works with no signal. Save results to a project and they sit next to the job’s materials list, tasks and timer. Several of the calculators also run in the browser, on the free web calculators page.
Get FieldDojo on the App Store → or on Google Play → — free on both.
All 65 calculators are free, work offline, and cite the code section on every result. FieldDojo Pro adds unlimited history, unlimited projects, cloud sync and the Pro report style and editor.